Wiring single-phase panels minimum requirements (design)

 

In this video you will see the working process for wiring a single-phase panel of minimum requirements. The images and designs are all made on the computer and not downloaded from the internet.

The synchronous voltage arrangement in the single-phase panel (does not include fuse) and is as follows:

1. Typical economic pina with material costs around 70 euros.
 Standard GACIA 2 row panel with:
✔️  3 x c10A fuses
✔️  2 x c16A fuses
✔️  General insurance c32A

✔️  Security - kitchen switch - water heater

✔️ Escape relay 2 x 40A

2. Exactly the same but with more expensive ABB materials and a difference of approximately +28 euros.
Standard 2-row ABB table with:
✔️  3 x c10A fuses
✔️  2 x c16A fuses
✔️  General fuse c32A
✔️  Fuse - kitchen switch - water heater
✔️ Escape relay 2 x 40A